Rabu, 08 Februari 2012

Berita

ELECTRICITY

Government to Build 93 Power Plants

The Ministry of Energy and Mineral Resources has issued Ministerial Decree No.02 / 2010 containing a List of Power Acceleration Program Projects including its related transmissions as a follow up to Presidential Decree No.4 / 2010 which forms a legal basis for the 10.000 MW Second Phase Acceleration Program.

Ministerial Decree No.2 / 2010 regulates that the power plant projects which are soon to be built will operate on renewable energy, coal, and gas.  A total of 21 power plants will be built by PT PLN, meanwhile a remaining 72 shall be built by a joint collaboration between PT PLN and private companies.  This Ministerial Decree is valid from January 27, 2010 up to December 31, 2014.

The following is a list of power plants forming the Second Phase 10.000 MW Acceleration Program, as stated in the Minister of Energy and Mineral Resources decree:


Projects carried out by PLN:
1.    PLTP Tangkuban Perahu I, West Java, capacity: 2x55 MW.
2.    PLTP Kamojang 5 dan 6, West Java, capacity: 1x40 MW dan 1x60 MW.
3.    PLTP Ijen, East Java, capacity: 2x55 MW.
4.    PLTP Lyang Argopuro, East Java, capacity: 1x55 MW
5.    PLTP Wilis/Ngebel, East Java, capacity: 3x55 MW.
6.    PLTP Sungai Penuh, Jambi, capacity: 2x55 MW.
7.    PLTU Hululais, Bengkulu, capacity: 2x55 MW.
8.    PLTP Kotamobagu 1 dan 2, North Sulawesi, capacity: 2x20 MW.
9.    PLTP Kotamobagu 3 dan 4, North Sulawesi, capacity: 2x20 MW.
10.    PLTP Sembalun, West Nusa Tenggara, capacity: 2x10 MW.
11.    PLTP Tulehu, Maluku, capacity: 2x10 MW.
12.    PLTA Upper Cisokan, West Java, capacity: 4x250 MW.
13.    PLTU Asahan 3, North Sumatra, capacity: 2x87 MW.
14.    PLTU Indramayu, West Java, capacity: 1x1.000 MW
15.    PLTU Pangkalan Susu 3 dan 4, North Sumatra, capacity: 2x200 MW.
16.    PLTU Sampit, Central Kalimantan, capacity: 2x25 MW.
17.    PLTU Kotabaru, South Kalimantan, capacity: 2x7 MW.
18.    PLTU Parit Baru, West Kalimantan, capacity: 2x50 MW
19.    PLTU Talakar, South Sulawesi, capacity: 2x100 MW.
20.    PLTU East Kalimantan (Peaking), capacity: 2x50 MW
21.    PLTGU Muara Tawar ad on 2,3 dan 4, West Java, capacity: 1x150 MW dan 3x350 MW.


Projects carried out by PLN in cooperation with private companies:

1.    PLTP Rawa Dano, Banten, capacity: 1x110 MW.
2.    PLTP Cibuni, West Java, capacity: 1x10 MW.
3.    PLTP Cisolok-Cisukarame, West Java, capacity: 1x50 MW.
4.    PLTP Drajat, West Java, capacity: 2x55 MW.
5.    PLTP Karaha Bodas, West Java, capacity: 1x30 MW dan 2x55 MW.
6.    PLTP Patuha, West Java, capacity: 3x60 MW.
7.    PLTP Salak, West Java, capacity: 1x40 MW
8.    PLTP Tampomas, West Java, capacity: 1x45 MW
9.    PLTP Tangkuban Perahu II, West Java, capacity: 2x30 MW
10.    PLTP Wayang Windu, West Java, capacity: 2x120 MW.
11.    PLTP Baturaden, Central Java, capacity: 2x110 MW.
12.    PLTP Dieng, Central Java, capacity: 1x55 MW dan 1x60 MW.
13.    PLTP Guci, Central Java, capacity:1x55 MW
14.    PLTP Ungaran, Central Java, capacity: 1x55 MW
15.    PLTP Seulawah Agam, Nanggroe Aceh Darussalam, capacity: 1x55 MW
16.    PLTP Jaboi, Nanggroe Aceh Darusalam, capacity: 1x7 MW
17.    PLTP Sarulla 1, North Sumatra, capacity: 3x110 MW
18.    PLTP Sarulla 2, North Sumatra, capacity: 2x55 MW
19.    PLTP Sorik Merapi, North Sumatra, capacity: 1x55 MW
20.    PLTP Muaralaboh, West Sumatra, capacity: 2x110 MW
21.    PLTP Lumut Balai, South Sumatra, capacity: 4x55 MW
22.    PLTP Rantau Dadap, South Sumatra, capacity: 2x110 MW.
23.    PLTP Rajabasa, Lampung, capacity: 2x110 MW
24.    PLTP Ulubelu 3 dan 4, Lampung, capacity: 2x55 MW.
25.    PLTP Lahendong 5 dan 6, North Sulawesi, capacity: 2x20 MW.
26.    PLTP Bora, Central Sulawesi, capacity: 1x5 MW
27.    PLTP Merana/Masaingi, Central Sulawesi, capacity: 2x10 MW
28.    PLTP Mangolo, Southeast Sulawesi, capacity: 2x5 MW
29.    PLTP Huu, West Nusa Tenggara, capacity: 2x10 MW
30.    PLTP Atadei, East Nusa Tenggara, capacity: 2x2,5 MW.
31.    PLTP Sukoria, East Nusa Tenggara, capacity: 2x2,5 MW.
32.    PLTP Jailolo, North Maluku, capacity: 2x5 MW
33.    PLTP Songa Wayaua, North Maluku, capacity: 1x5 MW
34.    PLTA Simpang Aur, Bengkulu, capacity: 2x6MW dan 2x9 MW
35.    PLTU Bali Timur,Bali, capacity: 2x100 MW
36.    PLTA Madura, capacity: 1x400 MW
37.    PLTU Sabang, Nanggroe Aceh Darussalam, capacity: 2x4 MW
38.    PLTU Nias, North Sumatra, capacity: 2x7 MW
39.    PLTU Tanjung Pinang, Riau, capacity: 2x15 MW
40.    PLTU Tanjung Balai Karimun, Riau, capacity: 2x10 MW
41.    PLTU Tanjung Batu, Riau, capacity: 2x4 MW
42.    PLTU Bangka, Bangka Belitung, capacity: 2x30 MW
43.    PLTU Ketapang, West Kalimantan 2x10 MW
44.    PLTU Petung, Kalimantan Timur 2x7 mW
45.    PLTU Melak, Kalimantan Timur 2x7 MW
46.    PLTU Nunukan, Kalimantan Timur 2x7 MW
47.    PLTU Kaltim, 2x100 MW
48.    PLTU Putussibau, West Kalimantan 2x4 MW
49.    PLTU Kalsel, South Kalimantan, capacity: 2x100 MW
50.    PLTU Tahuna, North Sulawesi, capacity: 2x4 MW
51.    PLTU Moutong, Central Sulawesi 2x4 MW
52.    PLTU Luwuk, Central Sulawesi, 2x10 MW.
53.    PLTU Mamuju, Sulawesi Barat, capacity: 2x7 MW
54.    PLTU Selayar, South Sulawesi, capacity: 2x4 MW
55.    PLTU Bau-bau, Southeast Sulawesi, capacity: 2x10 MW.
56.    PLTU Kendari, Southeast Sulawesi, capacity: 2x25 MW
57.    PLTU Kolaka, Southeast Sulawesi 2x10 MW.
58.    PLTU Sumbawa, West Nusa Tenggara, capacity: 2x10 MW
59.    PLTU Larantuka, East Nusa Tenggara 2x4 MW
60.    PLTU Waingapu, East Nusa Tenggara 2x4MW
61.    PLTU Tobelo, North Maluku, 2x4 MW
62.    PLTU Tidore, North Maluku, 2x7 MW
63.    PLTU Tual, Maluku 2x4 MW
64.    PLTU Masohi, Maluku 2x4 MW
65.    PLTU Biak, Papua 2x7 MW
66.    PLTU Jayapura, Papua 2x15 MW
67.    PLTU Nabire, Papua 2x7 MW
68.    PLTU Merauke, Papua 2x7 MW
69.    PLTU Sorong, West Papua 2x15 MW.
70.    PLTU Andai, West Papua 2x7 MW
71.    PLTGU Bangkanai, Central Kalimantan 1x120 MW
72.    PLTGU Senoro, Central Sulawesi, 2x120 MW.

The 10.000 MW Acceleration Program is part of the government’s effort to provide future national energy reserve to handle an annual growth rate of 6,8%.  The Presidential decree have regulated that this program is funded through the national budget, PT PLN, and other legal forms of funding which is regulated under relevant laws.

 