PLN Provides Premium Service for PT Krakatau Posco

JAKARTA. PT PLN (Persero) has made an agreement with PT Krakatau Posco (Posco) to distribute electricity from high voltage network 150 kV to electricity installation owned by Posco ocated in Cilegon. The agreement was signed by Director of Plan and Risk Management PLN, Murtaqi Syamsuddin and Director of Operation Java Bali PLN, Ngurah Adnyana with President Director of PT Krakatau Posco, Kim Dong Him in PLN Central Office, Jakarta, Friday (17/2).

PLN would distribute electricity for 165 MVA to Posco by Premium Service level. “The power purchase agreement between PLN and KP shows that businessman highly trust the capability of PLN to distribute electricity for its enterprise development based on its requested service quality level,” says Murtaqi.  

Premium Service is one of service given by PLN with installation quality, reliability guarantee and certainty based in Service Level Agreement (SLA) agreed by both sides. So that, PLN shows its commitment to become the stimulus of economic growth by fulfilling all industries’ electricity needs.

The electricity of 165 MVA would be used in three stages. Stage I, Posco would use electricity of 80 MVA by November 2012. Stage II, Posco would use electricity capacity of 100 MVA by July 2013. Then Stage III, Posco would use full power of 165 MVA by January 2014.

The electricity sales purchase distributed by PLN to Posco was agreed for Rp 810/kWh. This is the price agreement using Premium Service scheme. The sales price uses Single Tariff, in which the sale price in time of peak load (WBP) is equal to the price outside the peak load (LWBP). The power purchase agreement between PLN and Posco would be for 10 years and probably would be prolonged.

Besides, to increase the electricity supply reliability, PLN has permitted Power Plant owned by Krakatau Posco Power (KPP) to be synchronized with PLN electricity system. By this Premium Service, it proves that by business to business scheme, PLN do has capability to supply and distribute electricity power in quality and reliability guarantee as requested/hoped by customers, especially big customers with it quality level far better, not equal to standard service. PT Krakatau Posco is a joint venture between PT Krakatau Steel and Posco South Korea in steel industry. (AK)
PDFCetakE-mail